New Belgium Brewing

Improving Performance and Meeting Customer Demands

Goals

  • To increase the company’s ability to fully take advantage of manufacturing capabilities
  • Achieve Overall Equipment Effectiveness (OEE) to produce a quality product; manage production efficiency; and ensure production line availability through scheduled downtimes, package changes, and scheduled maintenance activities
  • To operate the brewery at full production capacity and double case production


Challenges

  • The brewery lacked real-time information on unscheduled downtimes at various equipment
    areas which caused production slowdowns
  • Production staff were continually reacting to unscheduled downtime at equipment areas
  • Management needed to address gaps in methods and processes to drive improvements
  • The bottling operation lacked the ability to predict capabilities to effectively commit brewery staff to specific production goals


Results

  • OEE increased from 45% to 65% in just over 2 years
  • Decreased downtime by more than 50%
  • Efficiency of scheduled run time increased by 25% - 30%
  • Achieved record production weeks producing 190,000 to 200,000 cases consistently,
    successfully meeting customer demands
  • Extended packaging area capacity to about 1.3 million barrels each year
  • The brewery was able to delay capital investments, enabling it to
    maintain lower operating costs

 